Here are more photo's
of the Boothbay home.
Roof sheathing is 5/8" thick and has a tongue and groove joint.
Primelock trim, Rite-flo drip edge, and ice and water membrane.
Working hard to get a roof on before the weather moves in.
As the roof nears completion, we begin with the interior prep for
plaster. The electrician installs wiring, the plumber
installs the plumbing, ventilation ductwork is installed, and
outside vents are put in.
After mechanical rough-in, we install an air/vapor barrier
and 1 x 3 strapping on the walls and ceilings before the interior
wall framing.
Framing for a curved plaster wall.
Notice how the vapor barrier is complete over and around the
interior walls.
When we install a range hood vent, we install it in
the wall behind the cabinets, not in the cabinet above the
range.
Details, details, details.